Free CompTIA Project+ Practice Test 2026

203 questions weighted to the Project+ PK0-005 objectives, from change control to earned value. Free to start, no account needed.

Try one now

Pick an answer

Who records decisions and action items during a meeting?

The Project+ exam at a glance

CompTIA Project+ (exam PK0-005, launched November 8, 2022) is CompTIA's entry-level project management certification for IT professionals. CompTIA's certification page gives a maximum of 90 multiple-choice and performance-based questions (the objectives document says up to 95) in 90 minutes, and the passing score is 710 on a scale of 100 to 900. The PK0-005 objectives cover four domains: Project Management Concepts 33%, Project Life Cycle Phases 30%, Tools and Documentation 19% and Basics of IT and Governance 18%, across both Waterfall and Agile methods. CompTIA recommends 6 to 12 months of hands-on experience managing projects in an IT environment, offers the exam in English, Japanese and Thai, and says the certification is good for life with no renewal.

Tigertest has 203 Project+ practice questions with explanations, free to start with no account required.

Exam code
PK0-005 (V5)
Questions
Up to 90, multiple choice and performance-based (the objectives say up to 95)
Time
90 minutes
Pass mark
710 on a scale of 100 to 900
Content
Project management concepts 33%, life cycle phases 30%, tools and documentation 19%, IT and governance 18%
Languages
English, Japanese, Thai
Experience
6 to 12 months managing IT projects recommended; no prerequisites
Valid for
Life, no renewal
Run by
CompTIA

Updated by the Tigertest team. Practice questions follow the CompTIA Project+ PK0-005 exam objectives (document version 7.0), the Project+ certification page and CompTIA's December 2024 Project+ article, checked November 2026. Exam rules change, so confirm current details with CompTIA: Project+ certification.

How It Works

Eight Drills

Methodologies; change, risk and issues; scheduling and quality; communication, teams and procurement; initiation and planning; execution and closing; tools and charts; and IT basics and governance. Questions you miss come back until you have mastered them.

Practice Tests

Two 90-question tests in 90 minutes with flagging and review, the length and pace CompTIA gives for the real exam. Questions mix every domain in the weights CompTIA publishes. Practice Test 2 is held out of the drills, so its questions are new to you.

Built on the Project+ Exam Objectives

CompTIA publishes the PK0-005 exam objectives with four domains and their weights. Every practice test follows them, from Scrum, Kanban and PRINCE2 to the change control process, RACI charts, PERT estimates, Pareto charts and cloud models.

Project Management Concepts33%
Project Life Cycle Phases30%
Tools and Documentation19%
Basics of IT and Governance18%
Tigertest mascot

Help Make Tigertest Better

Have an idea, a topic you'd like covered, or a question that could be clearer? We read every message and use it to improve every test.

Share Feedback

How to Pass CompTIA Project+

1. Learn the change control steps in order

Project+ asks what happens next: log the request, assess its impact, get a decision from the right approvers, update the plan, then implement and validate. Know when a change goes to the change control board and why scope creep is a failure of this process.

2. Know both Waterfall and Agile

The exam mixes plan-based and Agile questions. Learn when each fits, the Scrum roles and events, and what Kanban, XP, SAFe and PRINCE2 are known for, so a scenario points you to the right method.

3. Practice the few calculations

Cost variance (EV minus AC), schedule variance (EV minus PV), the PERT estimate (optimistic plus four times most likely plus pessimistic, over six), the critical path and team velocity are quick marks once practised.

4. Drill your weak area, then sit a full test

Tigertest tracks your accuracy by domain. Retake the drill you miss most until you clear 80 percent, then take Practice Test 2 cold. Project management concepts and the life cycle phases are almost two thirds of the exam, so give them the most time.

CompTIA Project+ Frequently Asked Questions

How many questions are on the CompTIA Project+ exam?

CompTIA's certification page says a maximum of 90 questions, multiple choice and performance-based, in 90 minutes; the PK0-005 objectives document says a maximum of 95. The exam is offered in English, Japanese and Thai.

What is the passing score for CompTIA Project+?

You need 710 on a scale of 100 to 900. The score is scaled, so it is not a fixed percentage of questions. Aim for 80 percent or better on these practice tests before you book.

What is on the Project+ exam?

Four domains in the PK0-005 objectives: Project Management Concepts 33 percent, Project Life Cycle Phases 30 percent, Tools and Documentation 19 percent, and Basics of IT and Governance 18 percent. The exam covers both Waterfall and Agile methods.

Does CompTIA Project+ expire?

No. CompTIA says Project+ is good for life and does not need to be renewed. There are no prerequisites, though CompTIA recommends 6 to 12 months of hands-on experience managing projects in an IT environment.

Is this practice test the same format as the real exam?

Each practice test is 90 questions in 90 minutes with free navigation and flagging, the length and pace CompTIA gives on its certification page. Most are multiple choice; a few ordering, matching and number questions stand in for the performance-based items. The questions are original, not CompTIA's.

Is the Tigertest CompTIA Project+ practice test free?

It is free to start, with no account required. Practice Test 1 and the methodologies, change and risk, scheduling and quality, and communication and teams drills are free; the initiation and planning, execution and closing, tools and charts, and IT governance drills and Practice Test 2 are part of Tigertest Premium, one payment with no subscription. Create a free account if you want your progress saved across devices.

I teach an IT project management or CompTIA Project+ course. Can my students use Tigertest?

Yes, for free. Make a class at tigertest.io/teach, post one link, and students join with just their name. You see who practiced, their test scores and the topics your class misses most.

Project+ sample questions and answers

6 of the 203 practice questions, one from each topic, with the answer explained.

  1. 1.

    A recurring outage keeps returning after each quick fix. What should the PM do next?

    • A.

      Run a root cause analysis

    • B.

      Raise the risk probability

    • C.

      Apply another work-around

    • D.

      Close the issue log entry

    Answer: A.

    Repeated failures after fixes point to an underlying cause. Root cause analysis finds it so the issue stops recurring; a work-around only bypasses it.

  2. 2.

    In Scrum, who decides the order of items in the product backlog?

    • A.

      Lead developer

    • B.

      Scrum master

    • C.

      Project sponsor

    • D.

      Product owner

    Answer: D.

    The product owner manages and orders the product backlog to maximize value. The scrum master coaches the team and removes impediments.

  3. 3.

    After a bug fix, testers rerun older tests to confirm nothing else broke. Which testing is this?

    • A.

      User acceptance testing

    • B.

      Smoke testing

    • C.

      Stress testing

    • D.

      Regression testing

    Answer: D.

    Regression testing checks that a change did not break features that worked before. Smoke testing is a quick check that a build runs at all.

  4. 4.

    Scope is unclear, so the buyer pays the vendor's hourly rate plus materials. Which contract is this?

    • A.

      Time and material

    • B.

      Fixed price

    • C.

      Cost plus fixed fee

    • D.

      Unit price

    Answer: A.

    Time and material contracts pay for hours and materials used, which suits work whose scope is not yet defined.

  5. 5.

    Approved scope, schedule and cost baselines are used for what?

    • A.

      Assigning blame

    • B.

      Writing the project charter

    • C.

      Choosing vendors

    • D.

      Measuring performance

    Answer: D.

    Baselines are the approved reference points that actual progress is compared with. They change only through change control.

  6. 6.

    Comparing final spending with the approved budget at closing is called what?

    • A.

      Cost estimating

    • B.

      Resource loading

    • C.

      Budget reconciliation

    • D.

      Earned value forecasting

    Answer: C.

    Budget reconciliation confirms final costs against the budget and closes out project accounts.

Every test on Tigertest is free to start, with no account needed.

See all 586 practice tests

Ready to Pass CompTIA Project+?

Start for free. No account required. 203 questions across all four domains.

Start practicing