  1. 1. A developer writes a code change and also moves it into production without anyone else reviewing it. Which control is missing?

    • A.Developer unit testing
    • B.Segregation of duties
    • C.Source version control
    • D.Documented rollback plan

    Answer: B. Letting the same person develop and deploy a change removes the independent check that stops unauthorized changes. Version control records the change but does not stop it.

  2. 2. Testing a single program module on its own, usually by the developer, is:

    • A.System testing
    • B.User acceptance testing
    • C.Integration testing
    • D.Unit testing

    Answer: D. Unit testing checks the smallest testable piece in isolation. Integration testing checks how modules work together.

  3. 3. Testing whether separately built modules pass data to each other correctly is:

    • A.Integration testing
    • B.Penetration testing
    • C.Unit testing
    • D.Acceptance testing

    Answer: A. Integration testing focuses on the interfaces between modules. Acceptance testing confirms the whole system meets the users' requirements.

  4. 4. Business users confirming that a new system meets their requirements before go-live is:

    • A.Integration testing
    • B.Regression testing
    • C.Acceptance testing
    • D.System testing

    Answer: C. User acceptance testing is performed by the business to sign off. System testing is done by the IT team against the full specification.

  5. 5. Running the old and new systems side by side and comparing their results is:

    • A.Pilot conversion
    • B.Phased conversion
    • C.Parallel conversion
    • D.Direct conversion

    Answer: C. Parallel conversion lowers risk because the old system stays in use until the new one's output is proven. It is also the most costly approach.

  6. 6. Rolling out a new system at one branch first, then to the rest of the company, is:

    • A.Pilot conversion
    • B.Direct conversion
    • C.Module-by-module phase-in
    • D.Parallel conversion

    Answer: A. A pilot uses one location or group as the test site. A phased approach brings in parts of the system over time across the whole company.

  7. 7. Which conversion approach carries the most risk if the new system fails?

    • A.Phased by module
    • B.Parallel conversion
    • C.Pilot conversion
    • D.Direct conversion

    Answer: D. A direct (plunge) conversion turns the old system off at once, leaving nothing to fall back on. Parallel running keeps the old system available.

  8. 8. Final testing should run in an environment that copies production as closely as possible. That environment is:

    • A.Developer workstation
    • B.Staging
    • C.Development
    • D.Production

    Answer: B. Staging mirrors production so final tests reflect real conditions without risking live data. Development is where code is written and changes often.

  9. 9. A documented way to restore the prior version if a release fails is a:

    • A.Release note
    • B.Rollback procedure
    • C.Baseline configuration
    • D.Change request

    Answer: B. A rollback procedure lets the team back out a failed change quickly. A baseline configuration is the approved reference set of settings.

  10. 10. An approved, documented set of system settings used as the reference point for future changes is a:

    • A.Version history
    • B.System component inventory
    • C.Change ticket
    • D.Baseline configuration

    Answer: D. The baseline is the agreed starting configuration that changes are measured against. An inventory lists components but not their approved settings.