1. What is the voice of the customer (VOC)?
- A.The team's view of quality
- B.Customer needs, stated or not
- C.Complaints sent to managers
- D.Sales figures by region
Answer: B. VOC is what customers need and expect, whether they say it or not. Complaints are one source of it, not the whole of it.
2. Customers say delivery is "too slow." Which critical-to-quality (CTQ) measure fits best?
- A.Size of the warehouse
- B.Driver satisfaction survey score
- C.Number of trucks owned
- D.Days from order to delivery
Answer: D. A CTQ turns a vague need into something measurable that the customer cares about: here, the time from order to arrival.
3. Why are customer needs translated into CTQ characteristics?
- A.To measure them
- B.So complaints stop at once
- C.So they need no data
- D.So the sponsor approves
Answer: A. Needs such as "fast" or "easy" cannot be tracked until they are stated as measurable characteristics with targets.
4. Which source gives a team direct voice of the customer data?
- A.Maintenance logs
- B.Payroll records
- C.Interviews
- D.Internal cost reports
Answer: C. Interviews, surveys and complaints come from customers themselves. Internal reports show the company's view, not the customer's.
5. A well-written CTQ characteristic is:
- A.Set by the team alone
- B.Fixed for many years
- C.Specific and measurable
- D.Broad and open to interpretation
Answer: C. A CTQ needs a clear measure and target that came from the customer, so the team can tell whether it is met.
6. Which problem suits a DMAIC project best?
- A.Recurring defects, cause unknown
- B.A one-time error already fixed
- C.A new product with no process
- D.A known fix awaiting approval
Answer: A. DMAIC fits an existing process with a measurable, recurring problem whose cause is not yet known. A brand-new process calls for design methods.
7. Why is a project with a very wide scope a poor first choice?
- A.It has no customer of any kind
- B.It needs no data to start
- C.Its savings are too small
- D.Hard to finish on time
Answer: D. Scope that is too wide spreads the team thin and delays results. Narrowing it to a manageable piece keeps the project on schedule.
8. Which data best shows that a problem is worth a project?
- A.How many teams are free
- B.Its monthly cost in defects
- C.How long the issue has been known
- D.Who first raised the issue
Answer: B. Projects are chosen for their impact on customers and the business, so the cost of the problem is the strongest case for one.
9. A suitable Six Sigma project should address a problem that is:
- A.Tied to one person's habits
- B.Measurable and recurring
- C.Already solved by experts
- D.Outside the team's control
Answer: B. A good project has data to measure, happens again and again, and sits in a process the team can change.
10. A team builds a new order entry screen. Who are its end users?
- A.Finance director who funds it
- B.The project sponsor
- C.The software vendor
- D.Clerks who key in orders
Answer: D. End users are the people who will use the result day to day. Their needs shape requirements even though they do not fund the work.